Alba’s Block 4 Project: Procurement and foundation works for main equipment completed

Manama, Mar. 20 (BNA): Aluminium Bahrain B.S.C. (Alba), the world’s largest aluminium smelter ex-China, stated today that its Power Station 5 (PS5) Block 4 Project is progressing as per schedule.

 

Block 4 Project’s EPC contractor Mitsubishi Power & SEPCOIII consortium completed the procurement process for the Project’s main equipment -- M701 JAC gas turbine, steam turbine and the turbines generators as well as 50% of the manufacturing process for the same equipment. Further, all civil foundation works for the main equipment for Block 4 Project were also completed by February-end 2023.

 

Commenting on this occasion, Alba’s Chairman of the Board of Directors Shaikh Daij bin Salman bin Daij Al Khalifa stated:

"Alba’s Block 4 Project has started to take shape with the completion of early milestones as per schedule; thus, allowing us to prepare for the major activities on site.

 

We look forward to safely delivering Block 4, a key Project under Alba’s ESG Roadmap, on schedule and as planned by Q4 2024."

Alba is also pleased to report that all milestones were achieved safely with the Block 4 Project having clocked 331,723 million hours without single Lost Time Injury (LTI) as of 19 March 2023.

 

Source: https://www.bna.bh/en/AlbasBlock4ProjectProcurementandfoundationworksformainequipmentcompleted.aspx?cms=q8FmFJgiscL2fwIzON1%2bDhHAn8fjsPLXCfP5h4NxrCk%3d

 

PLUS D'ACTUALITÉS

Share on FacebookShare on TwitterShare on Linkedin
Close

Read our latest publication

'FCCIB Members' Directory 2025'
Click here to view the online guide

Close

Consultez l'Annuaire des Membres 2025